\uD83D\uDDD3 Date

\uD83D\uDC65 Participants

\uD83E\uDD45 Goals

  • Progress updates

  • Get RPL members on the BIC server

  • Fundraising website setup

  • Rick Stamper meeting

\uD83D\uDDE3 Discussion topics

Time

Item

Presenter

Notes

Welcome/Attendance

Vann

  • Hello all!

Annoncments

Vann

  • Communications and marketing email

  • Meeting with Rick Stampter

  • Meeting with EHS tomorrow!

    • Possibility of a test site/pad install.


BIC Server Setup

Vann

Fundraising

Vann

Injector design

Tripton

  • Holes printed to small

    • Going to increase the sizing of the holes

Cold Gas

Colden & Jake

  • Started preliminary testing

  • USed adapter to get 1/2inch tubing to work

Injector

Cassie

  • Annulus finished

  • Only pintle left

Variable flow

Ceaser

  • Made a maple doc to do calculations

  • Estimating cost and mass

  • Preliminary model complete!

Nozzle/TCA

Evan

  • Machining ablator to size

    • Need to find way to safely machine

✅ Action items

  • tripton Draft Rev 2. send to Vann
  • Colden & Jake reprint nozzle and finish designing thrust rig
  • Cassie machining pintle with Ceaser
  • Ceaser Working on actual sizing
  • Vann Wellmon ox clean solenoids
  • Vann Wellmon Test ignitions devices
  • Vann Wellmon Meet with EHS
  • Vann Wellmon Bring power supply in to help Colden and Jake
  • Thomas makes a solenoid move with Labview
  • Vann Wellmon install compression springs on test stand

⤴ Decisions

  • No labels